Challenge and approach
The pilot had to put laboratories, the plant, and offices inside 2,000 m², with people and materials on separate paths. The cleanroom is Grade C and includes BSL-2. The target is PIC/S GMP.
The Taiwan team carried the design. Construction took 4 months, and design to validation took 7. The scope is HVAC and the cleanroom.
Scope
- HVAC
- Cleanroom
Duration
Construction 4 / Design to validation 7 months